issue with VL10b

Former Member
0 Kudos

Hi,

I am facing the very weird problem. i am using the retail envirnoment ecc 6.0.

i have scheduled daily batch job for outbound delivery creation from STO's through VL10B transaction.

As per the SAP standard system it should create a single delivery for one customer consolidating all STO's related to that customer/site.

but unfortunately system is not behaving like this and creating split deliveries for singel site/customer.

I have also checked the number of line items in the delivery they are much less than 999 so there should not be any reason to create split delivery.

can anybody guide in what aread i can look to resolve this?

thanks in advance

Praful

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

split Deliveries are created due to following criteria:

ship to party

Delivery date

Plant

shipping point

shipping conditions

Transportation grp

Loading grp

Item categories of materials

Please check the data

Regards,

Abhee.

Former Member
0 Kudos

hi Abhi ,

checked al the point you mentioned but all are same for both hte deliveries still there these are two diffrent deliveries.

strange!!!!!

praful

Former Member
0 Kudos

hi,

check whether splitting of deliveries is checked in customer master.

Regards

Anand.

Former Member
0 Kudos

Hi ,

thanks for your reply.

Where should i check this delivery splitting indication. i checked in shippin gdata of site customer but did not find

also i checkedin customization on delivery type but it it unchecked.