Hi SAP Gurus,
I have one req. as below,
I have one material which i want to run on both PD & VB type.
Means,
for simple example
1. I have one fert item in that one roh item bom.
first case:-
1. Roh item has min, max level is 500, 1000 ea. i.e. reorder level is 1000 ea.
2. if my roh has stock 400, system should generate requirement of 600.
3.& also if my fert item has 2000 requirement & if I take MRP RUN then system should genrate roh requirement is 600 & then 1000 nos.
Pls. advise me how i can achive this????
Thanks in advance.
Regards,
Vinayak
Hi,Vinayak
You have maintianed max lot qty is 1000 and then get that result you met.
Please maintain that field as blank and re-run MRP,check the result again.
Dick Hua
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vinayak,
I guess you dint get an ans to your previous posting on the same issue.
Anyways i see a fundamental mis-alignment in your need.
You specify Min stock level as 500, Max as 1000. If present stock level is 400 & req. coming for 2000, you want the system to propose 600 + 1000, which implies, when you issue the entire 2000, the system will have 0 stock, is that what you're looking for? Can you justify the same?
Regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.