EXTENSION OF NEW PLANT(DEPO)

Former Member
0 Kudos

Dear all

We have two plants( Manufacturing and spares)

To extend new plant(for depot) with new excise registration,in MM side, what are all configuring setteings required along with CIN settings

Please guide me

Is this come under Rollout Project? or Enhancement Project

Accepted Solutions (1)

Accepted Solutions (1)

kunal_ingale
Active Contributor
0 Kudos

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks for the response

Former Member
0 Kudos
Former Member
0 Kudos

hi

It will be rollout

Steps involved will be like

1) Define plant ( By copying from std plant)

2) Assign to company code

3)Create storage locations

4)Extend material to that plant

5)Maintain J1ID settings

also refer following

http://www.sap-img.com/materials/procedures-for-copying-one-plant-to-another.htm

Vishal...