Former Member
Feb 06, 2009 at 08:05 AM

Non accounting/ billing element shown in CJ30

34 Views

Hi all,

I have a project structure whereby some WBS elements are intended solely for the monitoring of project progress; hence they are not defined as planning/ accounting/ billing elements.

However, when I am in transaction CJ30 for project budgeting, these WBS elements are still shown, and budgeting can still be performed.

How can I define WBS elements so that budgeting is not allowed?

Many thanks in advance

- Daniel Koh