Is it possible to make Plant Maintenance Order Statistical

Hi All,

Is it possible to make Plant Maintenance Order Statistical so that cost will be directly booked to respective WBS elements *without* doing settlement.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Feb 06, 2009 at 09:08 AM

    don't think that is std in SAP

    however keep the PM order in CRTD phase which means you will not be able to post any cost on PM order

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 06, 2009 at 09:39 AM

    No need to do settlement to WBSE. Assign WBSE to PM order and in config transacton OPSV, mark the check box for order category 30.

    Sudhir

    Add comment