Scheduling of Planned Order for dependent material

11 Views

On exection of MRP, we are exepecting that Finish date/time of the dependent material's planned order should be the start date/time of the header material.

This is not observed

We are on ECC 6.0 and have Rep mfg with std routing. there are no inhouse time or schedule margin key values.