on 02-05-2009 12:51 PM
I have activated Committment Managment in AUC internal order type. and working fine at Purchase QA order level in DEV server. When PO is increase from budget amount system give error message.
In QAS i have checked all configuration but its not working in QAS. Please advise.
imdad
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The error message in DEV is probably due to active availability control. Can you compare the settings in the two systems under the following IMG path?
Controlling -> Internal Orders -> Budgeting and Availability Control
Go through the activities there and see if they are the same in both clients.
Regards,
Kenneth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I have activated Committment Update in Internal Order Type and controlling area as well in DEV and transported to QAS. It is working fine in DEV, system give popup message if Purchase Order is created exceeded budgeted amount.
In QAS it is not working. If I create an Purchase order exceeding budget system is not giving any error message.
What is missing in QAS. I have checked configuration is same in QAS and DEV
regards
User | Count |
---|---|