Skip to Content
avatar image
Former Member

Report for Service for a project

Hi,

I want to have a report which will give service PO qty value, All service line items Qty and value for that PO, total service entry sheet made and total invoice qty and value for a perticular project.Where can i get this.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Feb 05, 2009 at 11:27 AM

    hi kaplesh,

    press SAP1,SAP2 and goto MM services entry sheet...

    regrds

    pushpa

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Pushpa,

      all those reports is WBS selection criteria is not coming, Its showing all service entries

  • avatar image
    Former Member
    Feb 05, 2009 at 11:30 AM

    Use transaction ME2J

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 05, 2009 at 01:44 PM

    hi kalpesh

    1) see report me2s for all deatils.

    while u run this t-code, u have to enter the PO number & execute it.

    2) for list of services T-code MSRV6 / ml84 . here u have to put PO number OR select the particual vendor

    3) again for PO t- code MSRV3.

    Hope this will solve u r issue.

    regards

    parikshit

    Edited by: parikshit gaud on Feb 5, 2009 2:46 PM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 09, 2009 at 04:30 PM

    What is the Account Assignment Category in your Service PO?

    If you are generating Service PR directly from Project structure, then it will be Network Activity.In that case how can you get the list of Services per WBS element?

    This will be a development...

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 09, 2009 at 05:58 PM

    Hi Kalpesh,

    You can get the strandard cost element reports to check the servies you are to render from the vendor.

    Here in std sap we are using item cat D againt the Network if you want automatic PR so you need to go for Validations for this so that you can get reports against the WBS element.

    Regards,

    Muzamil

    Add comment
    10|10000 characters needed characters exceeded