on 06-19-2018 10:00 AM
Hi,
I have a question about the order status. Following situation:
1) create a SD order with a quantity from 200 pices
2) purchase requisition and purchase order will be created automatically with 200 pices
3) Inbound delivery with 100 pices
4) invoice with 100 pices
Now after the first invoice my SD order status switch to complete and fully invoiced. I thing thats´s not correct, because only 100 from 200 pices are delivered.
Does anyone have an idea where I can change the status logic? I check the postype and it seems OK.
Thanks
P.S. Dear Lakshmipathi, please don´t delete my question. I know google and also the search functions. To be honest, if I had find an answer to my question, I don´t ask.
Stephan
Read SAP note 151533 - Partially billed third-party orders are completed.
It explains the standard approach concept, the possible options to change it and even has a user exit example.
Still, in many cases setting a hard rule that an order can be completed only after the complete quantity is delivered, could cause more harm than good.
Before going with such change I would discuss the topic with Finance and Sales if I were you...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Can you share a screenshot of the Item category?
Regards
Kamlesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Along with that, what is the Partial delivery per item field says in XD02>>Sales Area data>>Shipping tab.
You can check this with a regular sales order for the same customer (without PR creation) for some 10 SO qty followed by delivery for 5qty.
One small request-PO creation with SO-the docs you implemented-Pl share with us.
Pl Confirm
Phanikumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Phanikumar,
thanks for your answer. Here you will find the XD02 settings, for me looks OK 2018-06-19-12h43-42.png.
Stephan
Sorry, please check the billing relevance as well. What is the value in your item category?
Below an extract from the help, for value F for instance:
"F: Relevant for order-related billing - Status based on invoice receipt quantity
Relevant for order-related billing based on the invoice receipt quantity (third-party business). The system does not transfer the order to the billing due list until the vendor invoice has been received and processed in the purchasing department. After each invoice receipt, a customer invoice is created for the quantity that appears on the vendor invoice. The order has status "Billed" until the next vendor invoice is received."
Check it also in combination with the "Billing quantity" field in the copy control between Sales Order and Invoice at item level.
Best regards,Andrea
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
but if you see the help it says about 'F' "
After each invoice receipt, a customer invoice is created for the quantity that appears on the vendor invoice. The order has status "Billed" until the next vendor invoice is received."
According to this, if you post a new Goods Receipt and a new vendor invoice, the billing status should be open again.
If you want a different behaviour probably you should set Billing relevance 'B -
Relevant for order-related billing - status acc.to order qty.
Best regards,
Andrea
Is this IPO - Individual Purchase Order process? Or in this scenario, PO is standalone?
If this IPO scenario, what is the status of your PO? Is that PO status complete? If PO status is complete, was qty in PO is changed while adopting from PR?
In IPO, once PO is created. The status is controlled through PO confirmation status.
Thanks,
JP
Hello,
please check the completion rule in Item category customizing.
Possible values are:
Not relevant for completion
A Item is completed with the first reference
B Item is completed after full quantity has been referenced
C Item is completed after the target qty is fully referenced
D Item is referenced via contract release
E Item is completed after full target value is referenced
Best regards,
Andrea
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.