In the work order we need to calculate the overheads actual cost also apart from the planned cost, estimated cost. also let me know if we have to do any cofigurational changes for this to be done?

Thanks

Vishnu Kumar

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Feb 05, 2009 at 03:22 AM

    Hi,

    planned cost will be calculated automatically by the system

    Estimated cost has to be entered manually i.e before releasing

    the order.

    Actual Cost also will be calculated manually

    To calculate overhead cost costing sheet has to be entered in the actual costing variant.

    Try the steps mentioned below:

    Plant maintenance and customer service >Maintenance and service processing ->Maintenance and service orders >Functions and setting for order types >Costing Data for Maintenance and service orders-->Maintain Costing Variants.