How is the date under the tab "Person Assignment" determined?

50 Views

Hi,

My scenario:

The project has start and end date 27.11.2008 and 31.12.2009.

On the assigned network activity the the constraint dates "Must start on" and "Must finish on" are set to 27.11.2008 and 31.12.2009.

On the activity element the same dates as defined in the constraint on the network activity, occurs.

When I try to add a new person under the "Person assignment" tab, the date 27.11.2008 are determined by the system as default. As soon as I run time scheduling the date shifts from 27.11.2008 to 28.01.2009.

In the configuration of the network scheduling parameters (OPU6) the field "Start in the past", the value is set to 0.

How is the is the date in the "Date" field under tab "Person Assignment" on an activity element determined?