Dear All
I have been going through the this forum for understanding how to inmplement Individual capacity functionality for production order. but some how no thread provides the complete details.
I have a scenario of cellular mfg. where similar machines are clubbed together. I understand this can be achieved by Individual capacity functionality. But need steps involved to implement the same.
I will appreciate if some document or step by step approach can be provided.
I am also adding a detail of the query as well
" We have work center say XYZ where I perform milling operation. I have 3 milling m/c say 001,002,003. I have operation quantity is 150 piece.I want to specify that 40 pieces are to be processed on machine 001, 60 pieces on machine 002 & 50 pieces on machine 003.
How I can allocate this.Please help out.If possible please tell step by step procedure"
Regards,
Vivek