Hi,

Is there a table or other ways to download the relationship between materials and operations (results of component assignment) in routing?

Thanks!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Harvey,

Refer to table - PLMZ

If helpful award points

Regards,

Vivek

Former Member
0 Kudos

Thanks for you help. but still can not find the relationship in PLMZ.

Former Member
0 Kudos

Hi Harvey,

Table: MAPL - Links material (MATNR) with routing no. (PLNNR)

PLKO - Routing header table (Link with MAPL is via field PLNNR & PLNTY = 'N')

PLPO - Routing operations table (Link with MAPL or PLKO is via PLNNR)

PLMZ - Component allocation link via field PLNNR.

Hope it is clear now, if not do revert back.

If helpful award points

Regards,

Vivek

Former Member
0 Kudos

harvey,

If your query is answered, award points & close the thread.

Regards,

Vivek

Former Member
0 Kudos

Hello Vivek,

I thought PLMZ was useful, but why I can't see the component items and the operation no. in the screen of PLMZ? I have checked all the fields in PLMZ.

Could you help to check again? Thank you!

Former Member
0 Kudos

The link:

PLPO-(PLNTY, PLNNR, ZAEHL) -> PLMZ-(PLNTY, PLNNR, ZAEHL)

If helpful award points

Regards,

Vivek

Does it answer your query or any more issues?

Edited by: Vivek on Feb 6, 2009 3:55 PM

Answers (3)

Answers (3)

0 Kudos

Hi Harvey

    Table PLMZ stored the relationship between operation and  component ,but if you want get more detail ,you have to connect to table  STPO .

     The relationship as below:

      Table PLMZ ,key field :

        PLNTY  Task list type

        PLNNR  Group

        PLNFL   Sequence(it may have more than 1 sequence in a routing due to alternative or parallel sequence)

        PLNKN  TL Node -  Task list node (it stand for Operation , but not  simply equal to operation no,  Say in a routing ,there are 3 operations  0010 /0020/0030 ,in here ,for operation 0010 the TL node  is  1, but  if  you delete it and create an new operation 0010 ,it may become to 4. pls  link to table PLPO to get the operation no. )

        you can get below information :

        STLTY  BOM category

        STLNR BOM

        STLAL Alternative

        STLKN  Nodes

        WERK_STL Plant

       Connect to table STPO ,then you can get the material no and other things .

       

       Hope this can help you .

Joe.Li

Former Member
0 Kudos

Hi Everyone ,, is there any T-CODE , that I could run and see the relationship between Components (raw material) with the Routing or workcenter ??

Rosa E.

Former Member
0 Kudos

Hi Everyone ,, is there any T-CODE , that I could run and see the relationship between Components (raw material) with the Routing or workcenter ??

I need it for several items , not one ,,

Need a kind of report to get this ,

Will appreciate your support

Rosa E.

Former Member
0 Kudos

Hi,

The report CA80 gives you most of the details.

Let me know if this helps.

Regards,

Pradeep.