Issue in Current Budget updation of WBS element (CJ30)

159 Views

Which Function Module should be used to update current budget (as done using transaction CJ30)? Presently we are using KBPP_EXTERN_UPDATE_CO function module but we are facing an issue. The issue is there is a mismatch between CJ30 Current budget value and RPSCO table Annual value field. Kindly clarify the function module to be used for this purpose and the right table to verify the updated value (current budget).

Thanks in advance.