Rework

26 Views

Dear experts ,

The following is my client's requirement reg Rework.

Say, there is a production Order for FG001. (20 mm dia bar)

While entering the Rework qty operationwise in CO11N, there are 2 scenarios.

1.Rework for the same FG001. (20 mm dia bar)

- For this, they have opted for a separate Rework Order through Trigger point ,

which can be mapped in std SAP.

2.But, sometimes it is not possible to rework to the same FG ((20 mm dia bar).

So ,there is a possibility of converting (reworking) the rework qty to another FERT say,

FG002 (18 mm dia bar) to suit another requirement .

-They call this as salvaging process .

Example : ( for scenario:2)

There is a production Order with 5 operations for 100 Tons.

While entering the confirmation in CO11N , for the 2nd operation , they are entering the

yield as 75 Tons and rework as 25 Tons.

The remaining 3 operations will get completed with oprn qty 75.

Here ,at the time of entering the confirmation , they do not know to which FG the rework qty is going to be salvaged .

How to map this scenario ?

Thanks & Regards,

Sheik