We have created Preliminary cost estimate.
Also we selected radio button in REM profile " POST ACTIVITIES " / Using Data from Preliminary Costing"
Still when we do backflush, for GR , FG rate is considred as per standard cost estimate and not as per preliminary cost estimate.
Any other setting is required ?
thanks