Former Member

Material cost not showing as assigned cost

Hi All,

Whenever i am assigning a component to an activity the material cost is not comming as an assigned cost. But during PR it is comming as commitment. It seems like some CO settings.

Can anybody help on this pls?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Feb 03, 2009 at 08:36 AM

    Hi,

    If the material you attached is plant material (L) which will create 'planned order' / 'production order', it is standard system behaviour. This is to avoid duplication of planned cost as 'Planned order' / 'Production order' forms part of assigned value.

    Muarli

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 03, 2009 at 06:38 AM

    Which type of stock you are using ?

    Regards

    Nitin

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 03, 2009 at 06:51 AM

    Hi ,

    It seems that you trying to get planned cost by assigning a material to your network activity. If so and if you are not getting planned cost of the material in your project, then check whether material is having a value or not, secondly check network has been kept with to determine planned cost or not in control tab page. then kindly check which is the valuation variant maintained for the network plan.

    Best Regards

    Vicky

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Check the OBYC setting maintained with your MM consultant with proper GR/IR accounts and consumptions accounts, unless and until these accounts are not maintained in OBYC you will get those values against the WBS as all projects cost arebeing captured in cost elements.

  • avatar image
    Former Member
    Feb 03, 2009 at 07:55 AM

    can you tell me the details of the values that you are getting and which you expect, planned values against activity and material cost.........