Dear Experts,

Im not able to understand the concept of

Control indicator........CO Partner update function in OPSC.....?

Classification...?......Planning..?

Plz give some inputs with simple example if its possible.

Regards

Chandra

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Feb 03, 2009 at 05:20 AM

    Hi

    This is to care of the total quantity updates within CO. Direct activity allocations is done with KB21N.

    Take a example cost center supplies services to many networks. For those working with the cost center, the information on which order has received how much is of little interest. If you set the partner update in the order type for the small orders to "" Not active"or "Partly active", the system produces a cumulative totals record covering all the small orders and not individually. The partner information remains intact in orders, if you set the CO partner update to "partially active".

    Thus from cost center side you will be able to see the cumulative posting of quantity distributed amongst the orders.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 03, 2009 at 05:28 AM

    Classification :

    Classified orders can be selected in the information system for Controlling in a list showing all orders that have certain characteristic values and statuses.

    The values of the classified orders can be grouped with the following functions:

    Product drilldown

    Order hierarchies

    etc.

    Planning :

    Use this indicator to specify that you are only using the network for planning. All of the planned costs from this network will be appended to the WBS element, however, they do not raise the assigned values.

    It means that planning inidictor determinse weather the planned values of the network should be validates against the budget of assigned WBS during active availability check.

    planning ticked indicator can be called as planning netowrk whose planned cost will not included in the availability check.

    This type of network are perticularly relevent for hte project that utilise a non- valuatre project stock.

    Regards

    Nitin

    Edited by: Nitin Patoliya on Feb 3, 2009 11:17 AM

    Add comment