Budget by periods and availability check (AVC)?

HI ,

Can we have Budget by periods and with availability check (AVC)?

for ex: for

WBS element 1 for January -1000 USD for Feb 5000 USD. And so on...Total yearly budget is 15000USD.

And

WBS element2: January -1500 USD, Feb 2500 USD and so on ...total yearly budget is 25000USD.

If the budget Exceeds for the particular WBS element for the particular period then it should give message (error/warning/).

Can we implement this in Project system?

Thanks for your time

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Feb 03, 2009 at 03:05 AM

    To give budget by period (Month ) is not possible in PS. Budget is annual / overall in PS. you requirement can be achieved by monthly you provide budget to WBS in the form of supplement.

    This way indirectly you can achieve the same.

    Please refer this post.

    Project Budget by Month

    Regards

    Nitin

    Edited by: Nitin Patoliya on Feb 3, 2009 8:40 AM