Resource Related Billing

MohanDesai
Active Participant
0 Kudos

Hi! All,

In resource related billing where we can we look into the hours booked by the associates or how timesheet hours are linked to? Resource related also shall have to include the hours booked by the associates.

Thanks

Bekele

Accepted Solutions (0)

Answers (3)

Answers (3)

MohanDesai
Active Participant
0 Kudos

Ok

MohanDesai
Active Participant
0 Kudos

Ok

Former Member
0 Kudos

Hi Bekele ,

you can check CJI3 for the cost of hours booked on the Prjoject .

These costs will be represented in the Billing request based on the DIP Profile .

regards

Kish

Former Member
0 Kudos

Hi Kish,

do you know what causing qty of hours in CJI3 is different with available qty in DP91.

seems like my hour qty in RRB is less than in CJI#.

thanks

nadifa.