Hi PP expert,
i want to create long term planning,1st i have done PIR with inactive version with T code MD61,
then i created planning Scenario with MS31,
then i did copy version from 00 to 03 with t code MS64,
then i did planning run with t code MS01,
then in MS04 show planned order......now i have confusion...how this planned order will be convert in production order.when i want to simulate this planned order in production order its open change planned order......also do not show purchase order of that component,
kindly suggest me what do to...
1st time i doing long term planning....
regards