Set activity TECO and the assigned material is gone

Dear all

could you help me on this issue.

when the project is almost complete, i set TECO to the WBSE or to the activity, at the same time, the material assigned to the activity is disappeared.

is it correct? i cannot find the relevant notes.

can anyone explain it ?

thanks

Judy

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Feb 02, 2009 at 06:28 AM

    Hi

    This is std. behaviour. The material component gets deleted once you set TECO to project. (this means there should not be any committements).

    The deleted component disappear from the structure because of system setting. You can change it to make the deleted component visible. In CJ20N-Setting-Options--Display deleted objects.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 02, 2009 at 07:02 AM

    Just in addition to Hemant TECO status does not allow any planning activities, so, if you set it on network along with material req. it deletes capacity requirement.

    Regards

    Nitin