Set activity TECO and the assigned material is gone

Former Member
0 Kudos

Dear all

could you help me on this issue.

when the project is almost complete, i set TECO to the WBSE or to the activity, at the same time, the material assigned to the activity is disappeared.

is it correct? i cannot find the relevant notes.

can anyone explain it ?

thanks

Judy

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

This is std. behaviour. The material component gets deleted once you set TECO to project. (this means there should not be any committements).

The deleted component disappear from the structure because of system setting. You can change it to make the deleted component visible. In CJ20N-Setting-Options--Display deleted objects.

Regards

Former Member
0 Kudos

Thanks for both of us.

Judy

Answers (1)

Answers (1)

nitin_patoliya
Active Contributor
0 Kudos

Just in addition to Hemant TECO status does not allow any planning activities, so, if you set it on network along with material req. it deletes capacity requirement.