Hi All,
I have scenario, in stock transfers from plant to depot,
1) Depot send the indent to plant in excel sheets
2) Executive at plant makes the sto( in SAP for available products and remaining will put in pending orders( makes in excel sheet).
now the requirement how to map the above scenario in SAP.
REGARDS,
RAM
Dear Ram,
-->In SAP you can process this scenario through Stock Transport Order(STO).
-->You can treat Depo as one of the despatching plant.
-->You can do the STO process between two plants(i.e depo and maufacturing plant).
-->You can create Stock transport Purchase order from Depo plant to the Manufacturing plant
Based on the STO PO you can deliver the products from the manufacturing plant through replenishment delivery.
-->For STO related settings go through this IMG path
SPRO>IMG>Material management>Purchasing>Purchase order-->set up stock transport order.
I hope this will help you,
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Murali,
Thanks for ur response, actually whatever u said is the process which currently we are using, the problem with this process is once u create PO , the stock get allocated, but my requirement is that despatching must be flexible depends on the market demand we keep changing the despatching..
regards,
ram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.