on 01-30-2009 5:23 AM
Hi,
Through MD61 using either material number, product group , plan etc... we can update PIR s for limited part numbners only
is there any otehr transaction through which we can updated for mass
we have to update almost for 2000 parts
BDC also shall not be useful
any way to directly upload copying from some excel
any standard SAP transaction code for mass updation of PIR s?
regards,
madhu kiran.
marked as answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Either you can use the BAPI mentioned by our friend.
OR
Goto Tcode : MD61 and enter the Material / Plant and goto the intial screen and Copy paste the Material Number and Qty from An Excel sheet upto the number rows displayed in MD61 screen and press enter and then Click Page Down Ikon, system will show the new rows where you can copy and paste again from the Excel sheet and Repest the steps to complete 2000 materials.
OR
You can create the BDC , BDC will work for Tcode : MD61 .
Hope this will help you.
regards
radhak mk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Did you try with the "BAPI_REQUIREMENTS_CREATE"?
-Thaila Shree
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.