How we can use parallel seq in capacity planning?we have two machines which can be run parallel for production ,now how to distribute capacity load? suppose for the production of 100 km,we required 1000 min when it is produced through only one machine.Now if 2 machines are used simultaneously we required 500 min.How to see this in capacity planning?