Plan Delivery Time

Former Member
0 Kudos

Can it be possible by some means to update the Purchasing Inforecod Plan Delivery time based on actual Goods receipt. I am working on SAP ECC 6.0

This has been stated as Advance functionality of ECC 6.0

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

The planned delivery time which you maintained in the Material Master MRP 2 is the exact Planned Delivery Time.

If you want to take the current delivery time you can check through MB51

Since the direct updation in Info record is not possible other than Price.

Regards,

Mohd Ali.

Former Member
0 Kudos

Why do u want to change the Pld delivery time in info record.Because Info record Plznned delivery time will be Copied in to PO,S.A..........

When u do the G.R You may receive the material earlier or later..

I believe it is not feasible to Planned delivery time in PIR.