on 01-29-2009 8:32 AM
Can it be possible by some means to update the Purchasing Inforecod Plan Delivery time based on actual Goods receipt. I am working on SAP ECC 6.0
This has been stated as Advance functionality of ECC 6.0
Hi,
The planned delivery time which you maintained in the Material Master MRP 2 is the exact Planned Delivery Time.
If you want to take the current delivery time you can check through MB51
Since the direct updation in Info record is not possible other than Price.
Regards,
Mohd Ali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Why do u want to change the Pld delivery time in info record.Because Info record Plznned delivery time will be Copied in to PO,S.A..........
When u do the G.R You may receive the material earlier or later..
I believe it is not feasible to Planned delivery time in PIR.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.