Former Member
Jan 28, 2009 at 10:37 PM

Time-based maintenance plan

589 Views

Hi,

We are trying to schedule a time-based maintenance plan.

Firstly, we have created a measuring point as a counter to the equipment.

Also we have defined a maintenance strategy which involves hours in it

and finally we have assigned these strategies in a task list at operational level.

By t.code IP41 we assigned the counter and the task list into the maintenance plan.

However, when we want to create this maintenance plan,

the system asks to define an annual estimate.

If we define the annual estimate, system schedules a maintenance plan according to this number.

We want to schedule maintenance plan according to the counter only.

For example, if that equipment has a maintenance plan in 600 hours performance

and if the counter is at 600 hours, we want the system to schedule an order at that level.

Is it possible or do we have to set the annual estimate for maintenance plan scheduling?

How can we schedule a maintenance plan according to a counter and a maintenance strategy only?

Thanks,

Best regards

Begü