Hi,
I am budgeting at WBS levels in project using CJ30. In the tolerance limits, I have given Usage 100% and action 2 u2013 Warning with mail to person responsible. I havenu2019t given Error anywhere.
But, Still while I am posting to the network below the WBS whose limit is reached to 100%, I am getting error message saying budget exceeded. Even, I tried to give WBS element, getting same error.
Error message number: BP604
Please let me know if I am missing something in configuration
Thanks in advance,
Satya