on 01-28-2009 4:24 PM
Dear Experts,
i have a problam, while i execute ck11n for specific material number i found that the fixed cost is zero and the costing doesnt show the bom components
how can i fix this problam?
Regards,
Amir
Did you check on the PP side to see whether there is a BOM existed for the product?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check for the following:
1. Check material master Costing views to ensure that "do not cost" check box is not selected by mistake
2. Make sure that the BOM is Costing BOM or Production BOM or Universal BOM. Because some time the BOM may be engineering BOM or some other type which cannot be costed
3. Make sure that in BOM, they have selected the checkbox "relevant for costing" check box
4. It is also possible that the cost element that would carry the material cost is not assigned in Cost Component Structure
Let me know if the error persists even after checking the above issues
Best Regards
Surya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Amir,
Can check kp26 and kp06.
Even cost center planning and cost element planning also required.
Thnaks
Veeru
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi Venikat,
Thanks for your reply, yes i checked there is a BOM exist for this product
Thanks,
Amir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.