Dear Sir/Mam

How can we measure the overall efficiency for QM module through sap,related to user performance,cost,rework,rejection.

regards

kunal

Accepted Solutions (1)

Accepted Solutions (1)

former_member186399
Active Contributor
0 Kudos

Dear Kunal

please find the step wise for activating qm order

For appraisal cost,

1) Create an activity Type - Labour hours

2) Create a work center and attach the activity type in this

3) Attach this workcenter in the inspection plan

4) Create a QM order in QK01,

5) Put the relevenet datas as inspection type, material, cost center, order type , cost center, profit center

6) execute and assign the orders to the material

7) Do the result recording and save,. you wil get a pop for recording the activity type

regards

gajesh

Answers (3)

Answers (3)

former_member186399
Active Contributor
0 Kudos

Dear Kunal,

Yes you can activate QM order. Please find the link for the same. please go thru the same and let me know your queries

Link: [http://help.sap.com/printdocu/core/print46c/en/data/pdf/QMCOST/QMCOST.pdf]

Regards

gajesh

former_member186399
Active Contributor
0 Kudos

Dear Kunal

1) Hope you have rework order procedure to tackle rework process. if so then you will get the cost as the rework cost will be getting assigned to some cost elements. check with your PP and CO guys

2) It is very difficult to capture cost of inspection if you do not use QM orders.

A simple solution will be create a Z table and mantain for each inspection type a generic cost incurred for each lot. for eg 01 inspection cost 100 Rs, 04 inspection costs 200 rs so

and create a Z report for the same multiplying no of lots created for 01 inspection for a month with the cost you have maintained in the Z table. Take the help of an ABAPer in doing this.

Hope this helps you. please let me know your feedback

Regards

gajesh

Former Member
0 Kudos

Dear Sir

Can we activate QM order.how and where QM oder is utilised.

Regards

kunal

former_member186399
Active Contributor
0 Kudos

Dear Kunal

First please identify what all parameters you want to capture in the QM efficiency like Rework costs, rejection costs, quality scores , return goods costs , appraisal costs, notification costs etc

then let us discuss how to capture each one

hope this helps

Regards

gajesh

Former Member
0 Kudos

Dear Sir

During our implementation we have not used QM order cost,so can you guide how to check efficency of rework during inprocess inspection,incoming inspection and finished good,source inspection.

Regards

kunal

Former Member
0 Kudos

Dear Sir

During our implementation we have not used QM order cost,so can you guide how to check efficency of rework during inprocess inspection,incoming inspection and finished good,source inspection.

Regards

kunal