Scenario is ADSO > Open Hub Table > Third Party BI system

Delta works fine into the Open Hub Table.

However, how to process delta then onwards into the third party system, using an external ETL tool? Out of the box, there is no technical field with e.g. change date written to the Open Hub Table. What is the best way to identify delta in the Open Hub Table?
First guess would be to add an additional field in the transformation manually with the current timestamp. Is there any better way?

Thanks in advance!