on 01-28-2009 9:36 AM
Hi Gurus
I need to Delete/Reverse/ cancel PS Budget Document created through cj34. Kindly respond me immediately.
Hi,
-
We can return the budget in the project via CJ38
-
Enter the necessary data and choose Return. The Change Return: WBS Element Overview screen appears.
-
Enter the corresponding data.
Note: Only the WBS elements where the Budget Return business transaction is allowed are ready for input.
-
To select the timeframe for which you want to enter a return, choose Annual values -> Previous or Next.
-
Enter the returns and choose Continue. And Save the returns.
Also you can return the budget from the project using CJ35.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If u have transfered the budget from WBS A to B in CJ34, then u have to retransfer budget from B to A to reverse/cancel the transfer.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.