Dear All,

Please help me with this issue. The requirement here is from PR (with WBS Element) --> Contract --> PO (partial payments, total will be contract value which is adopted from PR)

How do i automatically close PR once this PR has been adopted into a contract and saved.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Noted. However by changing that system msg, the PR checkbox is still unticked (not closed).

The reason why i need this checkbox to be ticked is that, in the PS module, the PR is still in the Commitment amount. It should not be there anymore....

Former Member
0 Kudos

hi

set message 06 076 as error in customization

sproMaterials ManagementPurchasingEnvironment DataDefine Attributes of System Messages

Vishal...