Dear All,
Please help me with this issue. The requirement here is from PR (with WBS Element) --> Contract --> PO (partial payments, total will be contract value which is adopted from PR)
How do i automatically close PR once this PR has been adopted into a contract and saved.
Noted. However by changing that system msg, the PR checkbox is still unticked (not closed).
The reason why i need this checkbox to be ticked is that, in the PS module, the PR is still in the Commitment amount. It should not be there anymore....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
set message 06 076 as error in customization
sproMaterials ManagementPurchasingEnvironment DataDefine Attributes of System Messages
Vishal...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.