on 01-28-2009 6:20 AM
Dear Expert,
When I going settle one asse through WBS element P05/00204/CB, I got the follwing problem in SAP
Down payment to recipient 802000000006 0 area 01 amount 5,142.74 not cleared
Message no. AW605
Diagnosis
All downpayments were not cleared for the asset under construction for the receiver 802000000006 0 in area 01. An amount of 5,142.74 was not cleared, or too much was cleared.
You can only completely transfer an asset under construction if you reverse the down payments in the current fiscal year beforehand.
Procedure
Clear the downpayments that you want to settle to receiver 802000000006 0.
-
Should I find the vendor? If yes, how can I find exact vedor.
Regards
David
many thanx
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi David,
system won't allow you settle down payments to the final asset.
clear the down pymnt first that was posted to the WBSE and subsequently settled to the AUC.
Go to CJIA (PAYMENT LINE ITEM REPORT) give ur wbse as selection. look for line items with value type 61. these will be ur downpayment lines. double click to go to the origial trxn to find the vendor or look in cjia itself in the vendor column.
clear the dnpymnt with some invoice and then run the settlement again.
Ravi Shrivastav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.