cancel
Showing results for 
Search instead for 
Did you mean: 

KKAX - WIP calculation

Former Member
0 Kudos

Dear Gurus,

This is MTS scenario, calculate cost at multiple level of production order as below said example.

u2022 FG material A & B

u2022 u201CAu201D -(2nd level) BOM component

u2022 u201CBu201D-(1st level) BOM component

For u201CBu201D material production order I am able to run KKAX, KKS2 & KO88. but for u201CAu201D I am able to run only KK2, K088 but not KKAX.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

As you mentioned "A" is a second level BOM. The production order for "A" there will not be any WIP, the production order might be delivered, that is the reason you are unable to run the WIP using KKAX t-code.

Always WIP will be calculated for the open production orders only.

Regards,

V. Suresh

Former Member
0 Kudos

thanks suresh,

the problem is solved, Actually there were no material issue laying in production. Due to the same WIP was giving 0.