Jan 25, 2009 at 12:37 PM

Wait Time

616 Views

I have maintained Wait time, queue time and transport time for operation in routing, also processing time is also maintained.

When i do scheduling of routing it is not showing wait time either in scheduling overview or in Gantt chart.

When same routing is used in production order then also it did not show wait time in dates of operation segments.