How to assign material to project, checking the material availability in Project, moving the material from project to project?
Please guide me on same.
Prashant
material on project is assigned to network activities or can be also done in Easy Cost Planning without networks.
If using networks availability checks can be done using network type parameters and related configuration
To move material from project to project - this can only be done if using project stock functionality.