cancel
Showing results for 
Search instead for 
Did you mean: 

Customer Unloading Point Calendar

Former Member
0 Kudos

Hi,

I am trying to override SAP Standard Unloading Point Calendar in Sales order Schedule line. The SL is not considering the 'Z'calendar after performing ATP check. This is happening when there is only 1 schedule line whose RDD is in future. Could you please let me know if there are any User Exist or FM or BADI that overrides the standard SAP unloading point Calendar?

Regards

Madhura

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member

Hi Madhura,

You probably want to override first schedule line when a different unloading point calendar is used after initial ATP check. This is when the customer decides to change delivery window using an alternative unloading point calendar(2) after initial ATP check based on default unloading point calendar (1).

System considers alternative calendar in the scheduling but when it comes to final result, all times are as per first calendar. This happens only when RDD is confirmed for the same date.Is that correct?

This is due to the fact that SAP never changes requested line and stops updating requested line throwing a warning message.

I am also looking for enhancement spot or user exit or FM for the same.

Regards,