Distribution of work over duration

39 Views

Dear All,

In my present set up, when i distribute the work over the duration of the activity, the distribution is linear.

Ex- 50 m3 of excavation in 5 days will get distributed as 10 m3 daily for 5 days.

How can I make the distribution variable ( S-curve, or sinusoidal etc)???

Regards,

VikasDev