Dear all,

When I give activity price in KP26 for an activity for 1 month, it is taking average for all the 12 months.

For example: for 10th month i gave 100 rs and i want also rs 100. But it is dividing by 12 and taking 8.33. what to do?

Please suggest.

I checked activity prices strategy in the vauation variant. It is given as plan price for the period only.

Thanks & Regards,