Restriction of Production order confirmation till external processing completion

465 Views Last edit Jun 07, 2018 at 07:10 AM 2 rev

Hi,

As per requirement, operation has been done by vendor as an external subcontracting through subcontracting PO. I have to do GR against subcontract PO then system will change the operation status as "EODL" External operation delivered. After done with GR for the external operation then have to do proceed our in house operation confirmation. Can you share your suggestion to make restriction?

Ex:

There are 3 operation 10,20 and 30. here, 20 is external processing.

My requirement is, Order confirmation need to be deny for in house operation(30) without Subcontracting PO GR(Means order status EODL).

Best Regards,

Kavi.