Jan 23, 2009 at 12:06 PM

cProjects Actual Cost = 0 after Settlement Run

45 Views

Hi Gurus

After running Transaction CJ8G (Settlement Run), then I log into cProjects, locate my Project and go to the Accounting Tab, I click on Calculate, then Save, then I return to the cProjects Dashboard

When I look at the Actual Costs Value it is zero.

What do I need to do to prevent this from happening?

My overall process is.

Approve Time: CATS_APPR_LITE

Send Confirmed Time to cProjects SE38 - (DPR_CATS_CPR_TRANSF)

Transfer Timesheet Data to Controlling CAT7

Log in to cProjects

Locate the Project in question and go into Accounting

Click on Calculate & Save

Click on Home (Actual Costs > 0)

Generate Settlement Rules CJB1

Execute Settlement Run CJ8G

Log in to cProjects

Locate the Project in question and go into Accounting

Click on Calculate & Save

Click on Home (Actual Costs = 0)

Many Thanks in advance

Panduranga