Is it possible to maintain sequence of maintaining different views in material master.

For example: Basic Data 1 should be maintained first & then Basic Data 2 and then General Plant Data/Storage 1 and then General Plant Data/Storage 2 and so on.

If the user misses the sequence, it should give a error message.

Regards

Pradipta Sahoo

Accepted Solutions (1)

Accepted Solutions (1)

former_member1269942
Contributor
0 Kudos

hi

u can change ur material master screen squences as per u r want but ur second requriment is not possible as per my knowldge u can set sequences in OMT3B.

regards

sachin

former_member197663
Participant
0 Kudos

closing this message

Answers (1)

Answers (1)

ShekharDamale
Contributor
0 Kudos

Hi,

u r requirment is possible, that u change screen sequence of material master so the apperance will be as per u r requirement. In changes can be done in OMT3B in SPRO.