Resource assignment to work center

0 Kudos

Hi,

Can we assign more resources to one work center?

Prashant

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Surely. Goto CR02, enter work center and click on HRMS button, proceed to assign resources.

Regards

Answers (1)

Answers (1)

nitin_patoliya
Active Contributor
0 Kudos

Yes you can assign the resources to work center via HR assignment.

Got to CNR2 and click on HR assignment.

Regards

Nitin

0 Kudos

it is resolved