I have seen some threads related to Early Delta initialization in this forum. I have a question regarding this option.

To minimize the downtime/block users in the R/3 production system during set up tables fillup I would like to use the Early delta option. Please give your suggestions on the following procedure:

For Sales Orders, billing and Deliveries

1. Initialize Early delta in the BI system.

2. Go and fill setup tables

3. Do a full load to BI

4. Run delta job in R/3 (LBWE)

5. Run delta job in BI Info package

Do we miss any documents in this process for e.g. during set up tables fill up changes to existing documents or newly created sales orders.

I feel we won't miss. All changes will be reflected in Delta queue. And even newly created orders also will be coming to delta queue.

Please let me know if I am wrong.