Hi Gurus,

I have a requirement, that MRP should be active for only particular period.

For ex, For 6 months - a materials MRP should be active and next 6 months MRP should not be active.

Is there any way in SAP R/3 to do like this.

Regards,

Dinesh PP.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Nov 09, 2016 at 05:42 AM

    Dinesh,

    I would like to understand the business justification for this requirement. You can try by implementing BAdI MD_MRP_PARAMETERS, method ADJUST_MATERIAL_MASTER_PARAMS and change the runtime MRP type to ND (CH_MT61D_EXT-DISMM field, and CH_CHANGED = 'X') based on your requirements (date check) inside the BAdI.

    Best Regards.
    Rajen

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 11, 2016 at 09:02 AM

    Hi,

    You can place the demand for next 6 months and delete rest of demand from demand planning.

    other wise you can follow exit suggested by expert Rajen

    Thanks & Regards

    Sandeep Kumar Praharaj