Hi all,
I have a requirement to move (update) Project dates (either activity, network or WBS dates, preferably basic dates but also any other date) when a Purchase order confirmation date (acknowledgment date) is entered in the PO for a component/s related to a project. The need is to move forward automatically or by manual rescheduling relevant dates and to indicate potential shift in project completion based on late confirmation date for a component.
In other words - need to return to a project (in any place) the PO confirmation date. Any idea how to achieve this or any workaround?
Thank you in advance,
Jordan