Hi All
Whenever planned cost is calculated for project specific production order, the COGM value is always coming equal to all the debit values i.e.value of special stock taken together.
It is not considering the standard cost from material master maintained for the material thru costing run.
I am not able to understand how to make goods reciept with std cost maintained in material master.
Request you all to address my question please.
Regards
Rakesh