Hi,

We are in ECC 6.0.

In my system right now system is allowing user to change the price after GR and IR.

The client requirement is to provide the restriction to change the price in PO after GR(System should not allow user to change the price after GR has been post for any PO).

How i can achieve this requirement.

Need your expert help.

Thanks,

Add a comment
10|10000 characters needed characters exceeded

Related questions

10 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 20, 2009 at 02:26 AM

    You have to consider to use an user exit. In my opinion is more apropriated. you can make other changes and on PO and still receiving the remain quantities.

    regards

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 10:42 AM

    Thanks to all for quick response.

    Release strategy is already configured and the client requirement is to allow user to change the PO before GR,that's a reason i have not selected release indicator 1.

    Now how i can stop the user not to change the price after GR and Invoice has been posted.

    John,

    The message 06 207 is only applicable for stock material, but the requirement is for all kind of PO, including Service PO also.

    Please suggest me some more options to achieve this requirement.

    Regards,

    Add a comment
    10|10000 characters needed characters exceeded

    • Its a Standard Functionality and Cannot be Controlled.

      Either You set the Release Indicator to 1 Such that no Changes can be carried out Once Po is Created. But, Still you can Make Goods receipt.

      Or Set the Version Management for External Purchasing Documents.

      Apart From the above solutions there may be a chance to Control thru User Exits.

      I wud suggest to change the Release indicator to 1. If any Changes are needed then Cancel the Release and do the Changes again.

  • author's profile photo Former Member
    Former Member
    Posted on Jan 21, 2009 at 04:51 AM

    Hi Sanjana,

    I think user exit MM06E005 will help for your issue

    Regards

    Anand

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 10:24 AM

    Use release strategy with release indicator 1, system will not allow you to change the PO...

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 19, 2009 at 10:25 AM

    Set the message number as Error for 06 207 in SPRO>MM>Purchasing >Environment Data>Define Attributes of System Messages

    T code:OME0

    Activate version management or release procedure for the changes.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 19, 2009 at 10:28 AM

    hi

    why dont u setup release startegy

    by using it u can set the block for the PO

    in release indicator the chanability option give as 1 i.e. not changable

    http://www.sap123.com/showthread.php?t=59

    or u can also impliment the version management so that u can track the changes easily

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 20, 2009 at 03:26 AM

    All experts,

    Can anybody help me to find out the user exit to achieve this requirement.

    Thanks,

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 21, 2009 at 04:36 AM

    Hi experts,

    Please help me to find out the user exit to achieve this requirement.

    Thanks,

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 22, 2009 at 04:17 AM

    Thanks for quick help,

    Can anybody tell me which component to be used in this user exit MM06E005 and what would be the logic to achieve this requirement

    Thanks..

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 18, 2009 at 08:57 AM

    Thanks to all

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.