PROBLEM IN SERVICE P.O

Former Member
0 Kudos

Dear cons

We want to create a service P.O. by activating unlimited service item qty & maintaining overall value limit. When we will create a service entry sheet w.r.t P.O the system will check the value limit. When the value of the entire serv ice entry sheet will same as the over all limit at that time system will not allow to create service entry sheet further. Because it has already reached the overall value limits. if we activate the unlimited qty as well as mainting value limits which is not available in standard system so we want to make some enhancement. Pl. provide me some solution in this regard. Which user exit we will use.

nrk

Accepted Solutions (1)

Accepted Solutions (1)

kunal_ingale
Active Contributor
0 Kudos

hi

try using frame work order document type

it will allow u to give overall value limit

create the service po for this doc type and try

regards

KI

Answers (1)

Answers (1)

raghavendra_praveen
Active Contributor
0 Kudos

Hi

Try with this.. for unplanned services

Create service PO with limits (with overall limit and expected value). You can enter service entry sheets until the overall value is not exceeded for these services. If you enter service number then check the indicator unlimited overfulfilment indicator in services tab. But with service number i dont think you can have limits activated.

Thanks